- CFA Exams
- CFA Level I Exam
- Topic 9. Portfolio Management
- Learning Module 6. Introduction to Risk Management
- Subject 2. Risk Governance
CFA Practice Question
A risk management committee should discuss key risk issues ______.
B. at the board level
C. among employees
A. at the management level
B. at the board level
C. among employees
Correct Answer: A
A risk management committee should be run at the operational level.